This report details the Standard Operating Procedure (SOP) Version 2.0 for developing and revising Science Based Targets initiative (SBTi) standards. It defines governance roles, public consultation requirements, and processes for substantive, non-substantive, and urgent revisions to ensure technical rigour and transparency in corporate climate target-setting.
Please login or join for free to read more.
OVERVIEW
Introduction
The Standard Operating Procedure (SOP) for the Development and Revision of Standards V2.0 sets out the formal processes for creating, maintaining, and updating Science Based Targets initiative (SBTi) standards. The scope includes foundational standards, such as the Corporate Net-Zero Standard, as well as sector-specific standards and specifications. These procedures are informed by the SBTi vision of a net-zero and equitable economy by 2050, aiming to accelerate corporate climate action to limit temperature increases to 1.5°C.
The SBTi system functions as an integrated framework of normative documents, technical resources, and governance arrangements. It comprises the SBTi Standards System and the Methods, Metrics and Pathways Framework. While standards establish requirements for companies, the pathways framework provides the technical foundations necessary for setting targets.
Definitions
The document provides precise definitions for key terminology used within the SBTi ecosystem. Adoption is defined as the formal acceptance of a document by the Board of Trustees, while approval refers to permission from a relevant decision-making body to proceed to the next step. Other defined terms include criteria, which are mandatory requirements companies must meet, and mitigation pathways, which represent quantitative trajectories for climate-relevant variables over time. Revisions are categorised as substantive (full/extensive or limited) or non-substantive.
Roles and responsibilities
Governance of the standards process is divided across several key bodies. The SBTi Board of Trustees is the ultimate governing body responsible for managing the charity’s business and formally adopting standards. The Board reserves the right to reject standards based on legal considerations or alignment with the mission but cannot amend them directly. The Executive Leadership Team (ELT) manages resource stewardship and mitigates technical project risks.
The Technical Council serves as an independent deliberation and decision-making body with delegated authority to review and approve standards in the public interest. The Technical Department, led by the Chief Technical Officer (CTO), is the operational body responsible for research, development, and maintenance of the system. Finally, the Scheme Integrity and Operations (SIO) team ensures consistency across the governance framework and maintains this SOP.
Approach to SBTi standards development and revision
SBTi standards aim to provide requirements for non-state actors to align business practices with 1.5°C pathways. Technical decision-making is guided by principles of integrity, impartiality, proportionality, timeliness, stability, and transparency. Standards must be drafted to allow for assessment of conformity, minimise ambiguity, and ensure that relevant intellectual sources are appropriately attributed. Requirements must be informed by the best available science from authoritative sources like the Intergovernmental Panel on Climate Change (IPCC).
Overview of processes in this standard operating procedure
The SOP outlines five primary processes: new development, revisions, interpretations, urgent measures, and withdrawals. Revisions are further classified by their impact. Substantive revisions change the intent or applicability of a standard and require significant oversight, whereas non-substantive revisions are typically editorial or administrative and do not introduce new obligations.
Development or full/extensive revision of an SBTi standard
This process begins with background research, involving the compilation of data from monitoring, evaluation, and learning (MEL) activities and feedback from stakeholders. Project initiation requires a formal Project Initiation Document (PID) evaluated against strategic alignment, impact, need, risks, and feasibility. Following internal approval, a Terms of Reference (ToR) is developed and shared with the Technical Council.
The drafting phase may involve external advisory or working groups. Public consultation is mandatory for new standards, requiring at least one round of 60 calendar days and a second round of at least 30 days. For full revisions, a period of 30 to 60 days is required. Feasibility assessments, including pilot testing, are conducted for significant changes. Final adoption rests with the Board of Trustees following Technical Council approval. Once adopted, standards are published with a transition period to allow entities to achieve conformity.
Development or full or extensive revision of a sector specification
Sector specifications supplement foundational standards for sectors requiring specific criteria. If a specification is derived directly from a new pathway developed under the SOP for Methods, Metrics and Pathways (SOP MMP), it may follow a combined consultation and approval process. These specifications must utilise the foundational standard as a primary entry point and are restricted to criteria that add to or modify existing requirements.
Revisions of standards and sector specifications
Substantive revisions follow a process similar to new developments but may be abbreviated based on proportionality. Limited substantive revisions require a minimum 30-day public comment period. Non-substantive revisions, such as correcting typographical errors or providing clarifications, do not require a full PID or public consultation and are approved by the CTO.
Interpretations
Interpretations are formally issued normative explanations used to resolve ambiguities without introducing new requirements. The Technical Department documents the rationale for each interpretation, which must be approved by the CTO. Approved interpretations are published on the SBTi website and communicated to validation bodies.
Urgent measures
Urgent measures address time-sensitive issues where waiting for a regular review would cause serious harm. These include urgent limited revisions, suspensions of specific clauses, and group exceptions. Grounds for such measures include sudden threats to integrity, counterproductive effects on emissions, or incompatibility with new climate science. These measures require a 30-day public comment period unless extreme urgency justifies interim approval by the CTO and Chief Integrity and Partnerships Officer (CIPO).
Withdrawal of an SBTi standard or sector specification
A standard may be withdrawn if it becomes irrelevant, if its technical basis is untenable, or for strategic reasons. Withdrawal without succession requires a 30-day public consultation and a documented analysis of implications for entities holding validated targets. The Board of Trustees must adopt the decision to withdraw.
Continuous improvement
The SOP itself must be reviewed at least once every five years. Stakeholders can provide feedback at any time via email. The SBTi maintains a complaints system and ensures record-keeping for transparency. Final approved standards are kept for ten years, while process records are retained for at least five years.
Procedural departures in exceptional circumstances
Significant departures from these procedures must be approved by the CIPO and the Chair of the Technical Council. Such departures are only permitted in exceptional circumstances where conformity is impossible for reasons beyond the control of the SBTi. All departures must be documented in writing with a clear explanation.