Recharged: Repowering America's solar fleet with storage for a new era of demand
This report examines the US solar repowering market, estimating it could unlock 67 GW of solar and 92 GW of storage by 2040. It assesses technical potential, $346 billion in investment opportunities, and regulatory factors such as interconnection, permitting, and tax incentives under the One Big Beautiful Bill Act.
Please login or join for free to read more.
OVERVIEW
Section 1: executive summary
The United States’ solar fleet is currently entering its first significant replacement cycle. Many of the initial solar plants built between 2010 and 2016 are reaching the end of their technical and contractual lives. This transition occurs at a time when electricity demand is growing at a much higher rate than in previous decades, while new supply remains constrained by interconnection queues, permitting timelines, and supply chain bottlenecks. Repowering—which involves replacing aging equipment while retaining a site’s interconnection, permits, and land—represents a significant market opportunity. It is one of the few levers available that can add meaningful capacity on a timeline of months rather than years.
Our findings
Repowering could potentially meet one-third of the growth in peak demand driven by data centres by 2035. The process could unlock the equivalent of 9.6 gigawatts (GW) of new solar and 13.1 GW of dispatchable battery capacity by 2030. By 2040, these figures are estimated to rise to 67.0 GW and 91.7 GW respectively. This represents a $10.8 billion annual market in 2030, growing to $51.8 billion by 2040, representing a 17% compound annual growth rate (CAGR). The cumulative spend over the 2026–2040 period is projected at approximately $346 billion. Battery additions and replacements account for nearly half of this potential spend. The near-term opportunity is largest in distributed generation (DG), with three states—California, North Carolina, and Arizona—accounting for roughly two-thirds of the 2030 potential.
Repowering overview
Solar repowering refers to upgrading major equipment at existing plants to restore output or extend operating life. This can range from component replacements to array power uprates using higher-wattage modern modules. Because modern arrays produce more energy than existing interconnections can export at midday, adding a battery is often cost-effective. A repowered plant with added storage can deliver more than 50% more energy per year than the aged plant it replaces. Furthermore, the cost of repowering is meaningfully lower per watt than new construction because it avoids land acquisition and substation costs, though it does incur teardown and disposal expenses.
Section 2: sizing the repowering market
The repowering market is modelled bottom-up from the installed fleet. It assumes plants replace inverters and modules at age 15 (or age 20 for residential sites). Repowering erases accumulated degradation; for example, a 15-year-old array typically produces 11.00% less than it did when new. By 2040, the market mix inverts from being DG-dominated to utility-scale, as larger post-2017 cohorts reach repowering age. On a per-watt basis, a full repower costs roughly 20% less than equivalent new construction. Batteries are the largest single component of the spend, representing nearly half of the total investment.
Section 3: considerations for market participants
Owners and investors must evaluate how much can be rebuilt within existing permits without triggering new reviews. While like-for-like replacements can retain existing permits in most US markets, changes that increase capacity or add storage are treated differently. For early-market participants, distributed generation accounts for 52% of 2030 potential, meaning many decisions will be governed by state, utility, and local rules rather than RTO surplus processes.
Interconnection & permitting
Interconnection remains a significant advantage for repowering projects. RTOs and ISOs govern transmission-connected plants, and FERC Order 845 requires providers to offer surplus interconnection service. MISO’s Generator Replacement process allows new generation to connect at the same point of interconnection as a retiring resource, with 14.8 GW under study as of mid-2026. In contrast, distribution-connected plants are governed by varying state rules. For example, Maryland permits expedited review for systems as large as 10 MW, while New York triggers new applications for capacity increases above 2%.
Permitting and siting
Permitting for batteries is not standardised and is often decided by local authorities. The environment for new storage siting is tightening; as of mid-2026, there are more than 125 active battery storage moratoriums across 13 states. These restrictions target new siting decisions, which could benefit retrofits if they are treated as exempt from newer rules rather than requiring fresh discretionary permits.
Capital and financial structuring
Repowering sits on top of existing contracts and capital. Financing typically involves sponsor capital, incumbent lenders, and the monetisation of tax credits. For smaller projects, tax credit transferability has largely displaced tax equity. Lenders can often provide better terms for operating assets because they can underwrite against actual production history and new equipment warranties, which move failure risk back to the manufacturer.
Revenue considerations
Repowering extends an asset’s life by 15 years or more, requiring the extension of power purchase agreements (PPAs) and land leases. While PPA prices have risen roughly 40% since 2020, retail electricity prices also rose 9.0% year over year in early 2026. New revenue streams are emerging, such as PJM’s proposal to count repowered assets and storage as qualifying capacity for large loads, allowing owners to blend utility contracts with capacity sales to hyperscalers.
Tax incentives and equipment rules
The One Big Beautiful Bill Act (OBBBA, 2025) set deadlines for solar tax credits, requiring projects to have begun construction by July 4, 2026. However, storage tax credits remain intact through 2033. Storage installations can receive the full §48E credit, and transferability allows owners to sell these credits for cash. Prohibited foreign entity (PFE) rules and Section 301 tariffs on Chinese solar cells and batteries continue to influence equipment eligibility and market pricing.
Conclusion
The technical potential for solar repowering is substantial, with the ability to unlock 67 GW of solar and 92 GW of battery capacity by 2040. Repowering offers a faster and lower-cost alternative to greenfield development, enabling the grid to add capacity on a much shorter timeline than the multi-year queues faced by new projects.